Project Lead: Aldingbourne Parish Council Representative This project is to arrange a working party to tidy up the car park edge and to discuss funding opportunities with local authority for re-lining the car park and marking the disabled bays. Pot holes need filling, any other remedial surface work as required. Project on hold until after April Parish Council meeting. Update: August 2018 - lining is complete. Potholes still need to be filled.

| Planning: Summary sent to representative to discuss with Parish Council on Tuesday. [progressbar_striped width=”100″ color=”#000″ bg_color=”#d5d8dc” text=”100% complete.”] |
| Quotes: Quotes received from 4 of 4 vendors. [progressbar_striped width=”100″ color=”#000″ bg_color=”#d2b4de” text=”100% complete.”] |
| Project Approval: Negotiate funding opportunities. [progressbar_striped width=”100″ color=”#000″ bg_color=”#a3e4d7″ text=”100% complete.”] |
| Grant Applications: Submit grant applications (if applicable). [progressbar_striped width=”0″ color=”#000″ bg_color=”#fdedec” text=”N/A.”] |
| Funding Approval: Project approval from Trustees and Parish Council. [progressbar_striped width=”100″ color=”#000″ bg_color=”#82e0aa” text=”100% complete.”] |
| Installation: Installation progress. [progressbar_striped width=”50″ color=”#000″ bg_color=”#aed6f1″ text=”50% complete.”] |
| Completed: Completed or cancelled. [progressbar_striped width=”75″ color=”#fff” bg_color=”#17202a” text=”75% complete.”] |